Diamond Condominium – Construction Update:

Construction Update: 09.05.2017

  • Building B: Installation of internal walls: ongoing.
  • Building C: Installation of internal walls: 95% complete.
  • Building A1: 3nd floor slab complete.
  • Building A2: 5th floor slab and columns complete.
  • Building D1: 5th floor slab and columns complete.
  • Building D2: 3rd floor slab complete.
Construction Update 09 05 2017